EG40 Bore Pad, Eglinton

Benang built the EG40 bore pad at Eglinton, delivering service location, survey and soil testing, an upgraded access point with a new culvert, road improvements and a 200mm limestone pad inside an environmentally sensitive area with Aboriginal heritage conditions.

Sector
Utilities
Services
Civil
Location
Eglinton, WA
Dates
September to October 2022
  • Challenge

    The bore pad sat inside an environmentally sensitive area carrying Aboriginal heritage conditions and restrictions, so every clearing and access decision had to respect the approvals exactly.

  • Approach

    Benang completed the service location, survey and soil testing, upgraded the access point and installed a culvert near the existing road, improved the short road section at the bore site entrance, pruned trees for truck access and placed the 200mm limestone pad after environmental clearing.

  • Outcome

    The pad and access works were completed across September and October 2022 with no lost time injuries and no environmental incidents.

Roller, posi-track and loader working the cleared bore pad at Eglinton
3

Peak crew

30%

Aboriginal participation

Access upgrade and culvert works near the existing road
Limestone being spread across the bore pad
0

Environmental incidents

Compaction of the 200mm limestone pad
Plant working within the approved clearing limits
The upgraded access into the bore site
Road improvement at the bore site entrance
The pad taking shape at Eglinton
Completed bore pad and access at EG40