CivilUtilities

Kalgoorlie Potable Water Dam Civil Works

Benang delivered civil works at the Kalgoorlie potable water dam, cutting down the reservoir overflow level, installing an exclusion barrier at the overflow structure and applying fibre reinforced shotcrete to extend the life of the spillway chute.

Sector
Utilities
Services
Civil
Location
Kalgoorlie, WA
Dates
July 2022 to January 2023
  • Challenge

    The reservoir overflow level needed lowering and the ageing spillway chute needed strengthening, all delivered on a live potable water asset in Kalgoorlie.

  • Approach

    Benang cut and removed a section of the overflow structure to reduce the reservoir overflow level, installed an exclusion barrier at the overflow structure, and placed fibre reinforced shotcrete over prepared reinforcement to extend the spillway chute.

  • Outcome

    The works were completed across July 2022 to January 2023 with a peak crew of ten, no lost time injuries and no environmental incidents.

Reinforcement and formwork prepared along the spillway chute at the Kalgoorlie dam
10

Peak crew

20%

Aboriginal participation

Benang crew fixing reinforcement mesh over the spillway chute ahead of shotcrete at the Kalgoorlie dam
Shotcrete placed over the reinforced spillway chute at the Kalgoorlie dam
0

Lost time injuries

Works at the reservoir overflow structure
Exclusion barrier installation at the overflow structure
Spillway chute taking shape with fibre reinforced shotcrete
Crew working on the dam civil works at Kalgoorlie
Completed spillway works at the Kalgoorlie potable water dam