HV Cable Into A Live Substation, Henderson
Benang self-performed the contractor scope for Western Power's network support works at Cockburn Road, Henderson, installing around 2,240 metres of high voltage cable on a congested route with rail crossings, delivered around three Western Power outages in March 2026.
- Client
- Western Power
- Sector
- Utilities
- Services
- Power
- Location
- Henderson, WA
- Year
- 2026
Challenge
The cable route ran through high traffic areas past critical gas lines and overhead transmission, with rail under-bores to negotiate, and the works had to land inside Western Power's three-outage window in March 2026.
Approach
Benang self-performed the civil construction, cable installation, joint holes and reinstatement, boundary and rail under-bore surveying, service location with vac extraction around poles, inline cable jointing at drum locations, site restoration, and traffic management across the three Western Power outages, working under a rail safety management plan.
Outcome
Around 2,240 metres of high voltage cable was installed and pre-commissioned with core-to-screen and screen-to-earth 5kV tests, delivered to Western Power's outage program for switching, jointing and VLF testing across the March 2026 outages.

High voltage cable installed
Western Power outages delivered





Related projects